I-5 Corridor Improvements SR-134 to Buena Vista Street

May 18, 2017


Work will occur during daytime hours unless otherwise noted.


SR-134 to Magnolia Boulevard

Providencia Bridge:  Crews are working on the deck for the bridge.  

 Magnolia Boulevard to Buena Vista Street

 Empire Avenue: Crews are constructing approach slabs and constructing the bridge barrier.



Victory Place Separation:  Crews are backfilling abutment walls, erecting falsework, and removing shoring.

Northbound I-5 between Buena Vista Street and Cohasset Street: Crews are constructing retaining walls and removing trees and other vegetation along San Fernando Boulevard.

Southbound I-5 at Buena Vista Street:  Crews are constructing approach slabs and constructing the bridge barrier.

Southbound I-5 between Buena Vista Street and Burbank Boulevard:

Crews are placing lean concrete base.





SR-134 to Magnolia Boulevard


Northbound and Southbound I-5 Lane Closures.

Intermittent nighttime lane closures on both northbound and southbound I-5 -- weekdays from 10 p.m. to 6 a.m. and weekends from 10 p.m. to 8 a.m.

Intermittent Daytime Closures on Flower Street.

Flower Street under the I-5 bridge will be closed intermittently during the day from 9 a.m. to 3 p.m.

Magnolia Boulevard to Buena Vista Street

Buena Vista Street Closures.

Intermittent daytime and nighttime closures of Buena Vista Street, in both directions, between San Fernando Boulevard and Winona Avenue.    

Northbound and Southbound I-5 Lane Closures.

Intermittent nighttime northbound and southbound I-5 lane closures between Magnolia Boulevard and Hollywood Way from 9 p.m. to 6 a.m.

On- and Off-Ramp Closures.

Intermittent on- and off-ramp closures at Buena Vista Street, San Fernando Boulevard and Burbank Boulevard from 9 p.m. to 6 a.m.  Detours will be provided.

Empire Avenue Closure.

Empire Avenue between Wilson Avenue and Victory Place will be closed through fall 2017.  A detour will be posted.  