News

I-5 Corridor Improvements Between Orange County Line to the I-605

July 28, 2017


Week of July 30, 2017



FLORENCE AVENUE INTERCHANGE PROJECT

There are no closures scheduled the week of July 30. Crews have begun work to reconstruct the intersection of Fairford Avenue at Florence Avenue. Fairford Avenue will be reconstructed to meet the higher elevation of the new Florence Avenue Bridge.Fairford Avenue is closed to through traffic between Dollison Drive and Florence Avenue and will remain closed for reconstruction through early 2018. The closure area is shown in red on the map below. The detour route is highlighted in blue

Click to view large map.


Crews have begun work to construct the new sound wall. Over the next few weeks, crews will continue drilling CIDH (cast in drilled hole) piles along northbound I-5. This operation will be conducted weekdays, between 7 a.m. and 3:30 p.m.


A portion of the sidewalk on Longworth Avenue, adjacent to the northbound I-5, has been closed to accommodate sound wall reconstruction.  Crews have installed a chain link fence to close this area of the sidewalk from public access through the end of 2017. Beginning as early as Friday, July 28, crews will begin removing this portion of the sidewalk and the adjoining block wall, as they prepare to reconstruct the freeway sound wall at this location. Sidewalk/block wall removal work will take place weekdays between 7 a.m. and 3:30 p.m. and may be intermittently loud and disruptive due to concrete removal activities. The sidewalk will be restored once sound wall construction is complete.

IMPERIAL HIGHWAY & PIONEER BOULEVARD PROJECT

Crews will be  completing nighttime drilling operations for CIDH (cast in drilled hole) piles on Imperial Highway. This work will be ongoing for approximately four weeks and will require nightly closures on Imperial Highway, between Adoree Street and South Frontage Road. In addition, the contractor will be pouring concrete footings on Pioneer Boulevard and will close southbound traffic between Crewe Street and Imperial Highway for approximately three weeks (shown in red on the map below; detour route highlighted in green). Work will be performed Sunday through Thursday nights, between 9 p.m. and 6 a.m.

This information can also be found on the project Google map.


Click map to view project Google map.


Pile driving activity along I-5 at Pioneer Boulevard is ongoing; this work will be conducted weekdays between 7 a.m. and 3:30 p.m. and will be ongoing intermittently for approximately three more weeks. Please be advised this work may be loud and disruptive due to equipment noise, vibration, and pounding related to pile driving activity.

As crews work on Imperial Highway, Norwalk Boulevard and Pioneer Boulevard bridges at I-5, one lane in each direction will be closed on each street (at I-5) during the daytime, between 8:30 a.m. and 3:30 p.m.

ROSECRANS AVENUE & BLOOMFIELD AVENUE BRIDGE PROJECT

On Friday, July 28, at 2 p.m. crews will begin work to reconstruct N. Firestone Boulevard, between the main entrance of Norwalk Village Mobile Home Park and Rosecrans Avenue. In order to reconstruct the street, the main driveway for the Norwalk Village Mobile Home Park will be closed to all traffic through fall 2017. While this driveway is closed, access to enter and exit the community will be maintained via the back driveway near the storage lot. There will be no through access to Rosecrans Avenue from N. Firestone Boulevard, while this work is being conducted. The closure area is shown on the map below in red; the detour route is shown in green

Rosecrans Avenue may be closed to all through traffic (motorists and pedestrians) in both directions underneath I-5, Monday through Fridays between 10 p.m. and 5 a.m. Nighttime closures on Rosecrans Avenue will continue intermittently for the next six months. For detour information visit the project Google Map.

VALLEY VIEW AVENUE INTERCHANGE PROJECT

Pile driving and shoring activities are ongoing on the south side of Valley View Avenue. This work will be conducted weekdays during the daytime between 7 a.m. and 3:30 p.m. 

*DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather.



For information regarding upcoming closures, detours and other construction activity, be sure to check out the project Google map. This map will be updated in real time, with the latest information regarding project construction. Click the image below to view the map.