I-5 Construction Advisory - SR-134 to Buena Vista Street, November 10 - 17, 2017
November 10, 2017
Front Street Long-Term Closure: Front Street between the Metrolink station (south of the Magnolia Boulevard Bridge) and Burbank Boulevard will be a northbound-only one-way street. For access to the Metrolink station from northbound I-5 use the Olive Avenue exit to 1st Street and cross under the freeway on Verdugo Avenue. For access from southbound I-5 use the Verdugo Avenue off-ramp exit. Seismic retrofitting: Beginning in December 2017, crews will start seismic retrofit work on the I-5 bridge columns at Buena Vista Street and Winona Avenue. This work is necessary to ensure that the bridge's existing columns are more resistant to seismic activity. Expect delays on Buena Vista Street, Winona Avenue, and the I-5 northbound and southbound off-ramps. Additional information will be provided. here for more information.
Please remember, graffiti is a crime. Violators will be prosecuted. |
|
Work will occur during daytime hours unless otherwise noted.
Sonora Avenue, Alameda Avenue and Western Avenue Bridges: Through early 2018, crews are working in the I-5 median to demolish a portion of the bridges and working to construct and close the gaps in the middle of the freeway. LA River: Crews are constructing the walkway. I-5 Median (between Verdugo Avenue and Sonora Avenue): Crews are paving the roadway. Magnolia Boulevard to Buena Vista Street Victory Place: Crews are installing utilities and grading between Empire Avenue and Empire Center. Buena Vista Street: Crews are grading slopes and working on the sidewalks under the bridges. Southbound I-5 at Buena Vista Street: Crews are working on the freeway widening at the on- and off-ramps. Northbound I-5 between Empire Avenue and Cohasset Street: Crews are constructing and backfilling retaining walls. |
|
SR-134 to Magnolia Boulevard
Sonora Avenue and Western Avenue Closures:
Alameda Avenue Closures:
The following loop on- and off-ramps will be closed (RED in map below):
The following on- and off-ramps will remain open (GREEN in map below):
Magnolia Boulevard to Buena Vista Street
Northbound and Southbound I-5 Lane Closures:
East Orange Grove Avenue Closure:
Front Street Long-Term Closure:
Buena Vista Street Closures:
On- and Off-Ramp Closures:
Empire Avenue Closure:
|
|