Metrolink Assists 18-Million-Pound Advancement for Major Irvine Infrastructure Project

Crews work to restore Metrolink's two main tracks following the successful installation of the precast concrete box beneath the railroad in Irvine. The restoration process includes realigning the tracks, securing rail fasteners and preparing for welding to safely return the railroad to service.

Moving an impossibly heavy concrete structure beneath an active railroad is no small feat. But that's exactly what construction crews accomplished in October as part of the City of Irvine's Marine Way Grade Separation and Borrego Channel Project. The massive structure was pushed into place beneath Metrolink's Orange County and Inland Empire-Orange County line tracks, marking a major milestone in an infrastructure project that will eventually improve roadway connectivity and drainage near Irvine's Great Park.

The undertaking involved two separate construction milestones, each requiring a carefully coordinated 54-hour closure of the railroad. During a Sept. 12-13 work window, crews installed a precast concrete box weighing approximately 4 million pounds for the Borrego Channel drainage structure. Then, during an Oct. 10-11 work window, crews used an innovative hydraulic box-jacking method to push the nearly 18-million-pound Marine Way undercrossing structure into position in less than 24 hours, completing the installation three hours ahead of schedule. Once finished, the undercrossing will provide new roadway, pedestrian and bicycle connections between the Great Park area, Irvine Spectrum and Interstate 5.

While the scale of the construction is impressive, the work required extensive preparation well before the structures began moving. Signal and utility relocations were necessary to accommodate the new infrastructure, and teams had to carefully plan around the operational requirements of an active passenger railroad. With construction taking place directly beneath Metrolink's tracks, aligning the work with designated weekend closures was essential to minimizing service impacts and ensuring trains could safely resume operations.

The Marine Way and Borrego Channel installations represent significant progress toward improved connectivity in Irvine, but they also demonstrate what's possible when local agencies and regional transportation providers work together toward shared infrastructure goals. Through months of planning, technical expertise and close coordination with the City of Irvine and its project partners, Metrolink helped make these complex construction milestones possible while maintaining its commitment to safe, reliable passenger rail service.

The Marine Way and Borrego Channel installations represent significant progress toward improved connectivity in Irvine, but they also highlight the expertise and collaboration required to deliver major infrastructure projects alongside an operating railroad. Behind each successful construction milestone are months of planning and careful coordination across functional areas designed to keep Southern California moving.